A can do a work in 24 days and B in 40 days. If they work on it together for 10 days, then what fraction of work is left? - Study24x7
Social learning Network
3613 followers study24x7 12 Aug 2020 01:08 PM study24x7 study24x7

A can do a work in 24 days and B in 40 days. If they work on it together for 10 days, then what fraction of work is left?

A

1/2

B

1/3

C

2/3

D

3/4