If A can complete a work in 28 days and B can complete it in 35 days, then A will get how much money out of 4320 rupees if they both worked together in completing the work. - Study24x7
Social learning Network
29 Jul 2020 10:06 PM study24x7 study24x7

If A can complete a work in 28 days and B can complete it in 35 days, then A will get how much money out of 4320 rupees if they both worked together in completing the work.

A

1920 rupees

B

2300 rupees 

C

2400 rupees 

D

3000 rupees 