#CIVIL ENGINEERINGIn a CPM network latest finish time for an event 1is 10 weeks. Activity i -j takes 4 weeks for complation . Event J starts after 16 weeks. Float for activity i -j is - Study24x7
Social learning Network
07 Aug 2019 10:39 AM study24x7 study24x7

#CIVIL ENGINEERING
In a CPM network latest finish time for an event 1is 10 weeks. Activity i -j takes 4 weeks for complation . Event J starts after 16 weeks. Float for activity i -j is

A

2 weeks

B

6 weeks

C

10 weeks

D

12 weeks