Construction at base:- The cavity may be started from the top of foundation concrete& the hollow space, up to a level of about 100mm to 300mm below the damp-proofing course at plinth level, may be filled with plain cement concrete of proportion 1:2:4. But, as the cavity below damp-proof course does not serve any purpose ,the brickwork up to a level of 100mm to 300mm below the damp-proofing course at plinth level may be constructed solidly. The increased thickness of wall will also be helpful in supporting the load to be carried by the wall. - Study24x7