Probabilistic time for completion of any activity can be found out from - Study24x7
Social learning Network
04 Jan 2024 10:47 AM study24x7 study24x7

Probabilistic time for completion of any activity can be found out from

A

optimistic time

B

pessimistic time

C

most likely time

D

all of these

study24x7
Write a comment
Related Questions
500+   more Questions to answer
Most Related Articles