A and B can do a piece of work in 12 days and 16 days respectively. Both work for 3 days and then A goes away. Find how long will B take to complete the remaining work? - Study24x7
Social learning Network
27 followers study24x7 02 Jul 2021 10:56 AM study24x7 study24x7

A and B can do a piece of work in 12 days and 16 days respectively. Both work for 3 days and then A goes away. Find how long will B take to complete the remaining work?

A

15 days

B

12 days

C

10 days

D

9 days

study24x7
Write a comment
Related Questions
500+   more Questions to answer
Most Related Articles